Philadelphia Permit Report: October 2026, Urban Infill

By Ben C • Nov 5th, 2026
Market Monitor
Philadelphia
Permitting

Cedar Market Monitor · Urban Infill

The Cedar Market Monitor is a monthly newsletter for the people building Philadelphia's housing. We use public permit data to show where the market is heading: where new homes are going, how long approvals take, and who's building. This issue covers October 2026, with data through 6 November 2026.

Permit snapshot

Permits issued79vs 88 in Oct 2025 · 122 homesnew-construction building permits with at least one home, one per building
Last 3 months−15%216 permits Aug–Oct 2026, vs 253 a year earliernew-construction building permits with at least one home, one per building
Permit Issue time54 daysmedian SF, last 12 monthsL&I plan-review submission to issue date, one-home permits; only permits with a plan review (about half)
In the pipeline5,591permitted since Jan 2025, not yet finished

What got permitted

Buildings of two to four homes carried 71 of October’s 122 infill homes.

One home51Two to four homes71

Over twelve months infill homes are up 22%, and the missing middle (two to four homes) was 55% of them, up from 43% the year before. Homes, not permits.

Pipeline

5,591 homes permitted since January 2025 haven’t been finished yet.

5+ unit buildings3,728Single homes8972–4 unit buildings966

That’s the supply still coming: 80% of the 6,956 homes permitted in that time. 67% are in apartment buildings (5+ homes), and five ZIPs hold 39% of them, led by 19125 (551) and 19133 (495). Most permits get built: 79% of homes permitted 2016–22 were finished.

Teardowns

Five ZIP codes had 45% of Philadelphia’s 87 home teardowns in the last twelve months.

ZIPNov 2025 – Oct 2026Year before
1. 19125137
2. 1913488
3. 1914678
4. 1910463
5. 1914455

Private whole-house demolitions inside the City of Philadelphia, one per lot per year: 25 ZIPs in all (85 teardowns Nov 2024 – Oct 2025).

Permit issue time

A single-family permit takes a median 54 days to issue.

Building typePermits with a review timeMedian daysExcl. slowest 10%
Single-family178 of 5785444
2–4 units158 of 2587870
Multifamily & mixed use31 of 100103101

Median days from plan-review submission to issue, permits issued Nov 2025 – Oct 2026. The last column removes the slowest 10% to account for stalled applications. Review times come from the City’s plan-review records, which match 39% of the new-home permits issued in the last twelve months; permits without a plan review are not measured.

Where

Five ZIP codes carried 62% of October’s infill homes.

19103: 0 homes in October 202619104: 9 homes in October 202619106: 0 homes in October 202619111: 1 home in October 202619114: 0 homes in October 202619115: 0 homes in October 202619116: 0 homes in October 202619118: 1 home in October 202619119: 0 homes in October 202619121: 4 homes in October 202619122: 1 home in October 202619123: 7 homes in October 202619124: 0 homes in October 202619125: 13 homes in October 202619127: 2 homes in October 202619128: 0 homes in October 202619129: 8 homes in October 202619130: 0 homes in October 202619131: 0 homes in October 202619132: 6 homes in October 202619133: 38 homes in October 202619134: 1 home in October 202619135: 0 homes in October 202619136: 0 homes in October 202619137: 0 homes in October 202619138: 4 homes in October 202619139: 0 homes in October 202619140: 2 homes in October 202619141: 4 homes in October 202619142: 0 homes in October 202619143: 7 homes in October 202619144: 0 homes in October 202619145: 4 homes in October 202619146: 8 homes in October 202619147: 1 home in October 202619148: 1 home in October 202619150: 0 homes in October 202619151: 0 homes in October 202619152: 0 homes in October 202619153: 0 homes in October 202612345
None1–45–910–1920+
ZIPHomesShare
1. 191333831%
2. 191251311%
3. 1910497%
4. 1912987%
5. 1914687%

Fastest riser: 19133, from 48 to 71 infill homes in Aug–Oct 2026 against a year earlier. Only permits inside the City of Philadelphia are counted, so ZIPs that straddle the city line show the city’s part only. ZIPs come from each permit’s geocoded address.

Who’s building

Lynx Management Solutions LLC led with 51 homes in the last six months.

BuilderHomesPermits
Lynx Management Solutions LLC5116
DALE CORP5048
SZM Group LLC3815
BORCO CONSTRUCTION LLC3417
SPRUCE BUILDERS LLC3030

Infill homes permitted May – October 2026, out of 695. The permit holder is usually the general contractor rather than the developer, and one firm can appear under several names. 8 homes on 2 permits (1% of homes) name no holder and are not ranked.

Method. New residential building permits issued inside the City of Philadelphia, from the Department of Licenses and Inspections' permit records, filtered to buildings of one to four homes. Apartments (five or more homes) are left out. Demolitions and remodels are excluded from the permit counts. New homes built as an addition to an existing building count, as the Census counts them; an addition that only enlarges a house adds no home. Homes, not permits, unless stated.

3–4 unit rowhouse flats are buildings of three or four homes on a rowhouse lot: one structure with the homes stacked as flats, permitted as one building. Of the 417 permitted since 2023, 92% are three stories and 100% are attached or semi-detached. Where homes are grouped by size they fall in two to four homes, with 2-unit rowhouses.

Pipeline: homes on live permits issued since 1 January 2025, in buildings of every size, not yet finished: not yet recorded as a completed building on the Office of Property Assessment (OPA) roll, which records them with a lag, so some may already be done; permits outside the roll’s coverage and dead permits are left out. Teardowns: private whole-building demolitions of homes inside the City of Philadelphia, one per lot per year; the City’s own demolition program is left out.

Data through 6 November 2026. Built by Cedar.