Permit snapshot
What got permitted
Buildings of two to four homes carried 71 of October’s 122 infill homes.
Over twelve months infill homes are up 22%, and the missing middle (two to four homes) was 55% of them, up from 43% the year before. Homes, not permits.
Pipeline
5,591 homes permitted since January 2025 haven’t been finished yet.
That’s the supply still coming: 80% of the 6,956 homes permitted in that time. 67% are in apartment buildings (5+ homes), and five ZIPs hold 39% of them, led by 19125 (551) and 19133 (495). Most permits get built: 79% of homes permitted 2016–22 were finished.
Teardowns
Five ZIP codes had 45% of Philadelphia’s 87 home teardowns in the last twelve months.
| ZIP | Nov 2025 – Oct 2026 | Year before |
|---|---|---|
| 1. 19125 | 13 | 7 |
| 2. 19134 | 8 | 8 |
| 3. 19146 | 7 | 8 |
| 4. 19104 | 6 | 3 |
| 5. 19144 | 5 | 5 |
Private whole-house demolitions inside the City of Philadelphia, one per lot per year: 25 ZIPs in all (85 teardowns Nov 2024 – Oct 2025).
Permit issue time
A single-family permit takes a median 54 days to issue.
| Building type | Permits with a review time | Median days | Excl. slowest 10% |
|---|---|---|---|
| Single-family | 178 of 578 | 54 | 44 |
| 2–4 units | 158 of 258 | 78 | 70 |
| Multifamily & mixed use | 31 of 100 | 103 | 101 |
Median days from plan-review submission to issue, permits issued Nov 2025 – Oct 2026. The last column removes the slowest 10% to account for stalled applications. Review times come from the City’s plan-review records, which match 39% of the new-home permits issued in the last twelve months; permits without a plan review are not measured.
Where
Five ZIP codes carried 62% of October’s infill homes.
| ZIP | Homes | Share |
|---|---|---|
| 1. 19133 | 38 | 31% |
| 2. 19125 | 13 | 11% |
| 3. 19104 | 9 | 7% |
| 4. 19129 | 8 | 7% |
| 5. 19146 | 8 | 7% |
Fastest riser: 19133, from 48 to 71 infill homes in Aug–Oct 2026 against a year earlier. Only permits inside the City of Philadelphia are counted, so ZIPs that straddle the city line show the city’s part only. ZIPs come from each permit’s geocoded address.
Who’s building
Lynx Management Solutions LLC led with 51 homes in the last six months.
| Builder | Homes | Permits |
|---|---|---|
| Lynx Management Solutions LLC | 51 | 16 |
| DALE CORP | 50 | 48 |
| SZM Group LLC | 38 | 15 |
| BORCO CONSTRUCTION LLC | 34 | 17 |
| SPRUCE BUILDERS LLC | 30 | 30 |
Infill homes permitted May – October 2026, out of 695. The permit holder is usually the general contractor rather than the developer, and one firm can appear under several names. 8 homes on 2 permits (1% of homes) name no holder and are not ranked.